Tabuk Cement [4500 TPD kiln major shutdown of 450 Mt]

admin  -  Dec 13, 2011  -  No Comments

Client :Tabuk Cement

Project / Shutdown Details : 4500 TPD kiln major shutdown of 450 Mt.

Remarks : We undertook the relining of the total rotary kiln 35 m and maintenance job of Calciner, cyclone and cooler 100 Mt castable in 20 days including shell change for 10 days in between.